The week before launch is for checking, not building. By seven days out the thing should exist. The week is for testing it like a stranger would, scheduling your announcements, making a clear go or no-go call, and preparing for something to go wrong. If you are still building at three days out, move the date.
T-7: Freeze and test like a stranger
Stop adding things. Today you decide that what exists is what launches. Then go through it as someone who has never seen it. Open the link on a phone you do not normally use. Buy the thing with a real card if you can and refund yourself. Subscribe to the feed. Click every link on the page. Write down everything that is wrong in one list, and sort it into "must fix" and "later".
T-6: Fix the must-fix list
Only the must-fix list. Nothing else. If a must-fix item cannot be done by T-3, it is now a reason to consider delaying, and you want to know that today, not on launch morning.
T-5: Assets and copy
Gather everything launch day needs into one folder: the announcement post for each platform, the email to your waitlist, images in the right sizes, the launch link, any discount code. Write the announcements now, while you are calm. Read them out loud. Cut the first paragraph of each one; it is usually a warm-up.
T-4: Schedule and brief
Schedule the announcements that can be scheduled: the waitlist email, the social posts. Note the exact times. If anyone is helping you (a friend sharing it, a collaborator posting), send them the link, the copy and the time today. People need more than a day's notice to actually do it.
T-3: Go or no-go
Sit down and decide. Ask three questions. Does the core thing work end to end? Is anything on the must-fix list still open? Can you support it for the next week? If any answer is no, delay by a week and say so to your waitlist in one honest line. A delay costs you nothing. A broken launch costs you the people who tried it. Write the decision down with the date, so you do not reopen it at 2am on T-1.
T-2: Support and backups
Decide where questions will come to (one email address or one inbox, not five). Write short replies to the five questions you expect. Then plan for failure: What if the payment page breaks? What if the file will not download? What if the feed does not appear in the app? For each, know one thing you will do. Back up everything: the site, the files, the episode, the product listing.
T-1: Rest and final check
Do a last full run-through, the same one as T-7. Confirm every scheduled post is still scheduled with the right link. Charge your phone. Then stop. A tired launch is a careless launch. Tell one person who will check in with you on the day.
T-0: Launch day
Launch day is execution, not preparation. Post at the planned time. Reply to every comment, message and email yourself, quickly and warmly. Share what people say, with permission. Do not touch the product unless it is broken. Note what happens hour by hour. Then, when the day ends, close the laptop.
The checklist
T-7
- Feature freeze: nothing new gets added from today
- Full stranger test on a phone, including a real purchase or sign-up
- One list of problems, sorted into must-fix and later
T-6
- Must-fix list cleared, or a decision made about anything that cannot be
T-5
- Announcement copy written for each platform and the waitlist email
- Images, links and codes in one folder
T-4
- Posts and emails scheduled, with times noted
- Anyone helping has the link, the copy and the time
T-3
- Go or no-go decided, written down and dated
- If no-go: new date set and waitlist told
T-2
- One support inbox chosen; replies to the five likely questions drafted
- One fallback action written down for each likely failure
- Everything backed up
T-1
- Final run-through done; scheduled posts checked
- Early night
T-0
- Posted on time, every reply answered the same day
- Hour-by-hour notes kept for the post-launch review
What to measure
Keep it to four numbers. How many people saw it (views, opens, plays). How many did the thing you asked (bought, subscribed, signed up, pre-ordered). Where they came from (which post, which person, which community). And what they said, word for word. The last one is the one you will use most.
Do not judge the launch on day one. Look at the four numbers after seven days.
What to do this week
If your launch is more than a week away, pick your T-7 date and put each of the days above in your calendar. If it is this week, start at the day that matches today and do not skip T-3. The go or no-go call is the single step first-time launchers most often avoid, and it is the one that protects you.